生产计划管理

[复制链接]
发表于 2022-11-15 20:40:05 | 显示全部楼层 |阅读模式

马上注册,结交更多好友,享用更多功能,让你轻松玩转质量管理社区。

您需要 登录 才可以下载或查看,没有账号?立即注册

×
本帖最后由 gaowenhua 于 2022-11-15 20:42 编辑

会议主题控制、时间控制
  • 首先要明确召开生产协调会的目的,必须有时间限制。既然开会的时间短,参会人员就必须提前把会议材料如表单、数据等准备好
  • 其次要明确生产协调会的性质。生产协调会不是问题解决会,很多问题也不是半个小时能解决的。生产协调会的主要内容是总结前一天的任务,把次日的任务分派下去,有什么问题大家各自提出来。如果遇到必须解决的问题,那就要进行攻关,要开专题问题讨论会。



 楼主| 发表于 2022-11-15 20:41:43 | 显示全部楼层
Control of conference theme and time.
  • First of all, we should clarify the purpose of holding the production coordination meeting.  so there must be a time limit.d Since the meeting time is short, participants must prepare meeting materials such as forms and data in advance.
  • Secondly, the nature of the production coordination meeting should be clarified. . The main content of the production coordination meeting is to summarize the tasks of the previous day, assign the tasks of the next day, and put forward any problems. If we encounter problems that must be solved, we must tackle key problems and hold thematic discussion meetings.


 楼主| 发表于 2022-11-15 20:43:53 | 显示全部楼层
第二,横向控制法。
横向控制即参会的各部门要形成互相制约的关系。
生产协调会一般是计划部主持,生产部门、采购部、品管部、必须出席,有的业务部、技术部也会参加


 楼主| 发表于 2022-11-15 20:44:44 | 显示全部楼层
Second, lateral control method.
  • Horizontal control means that the participating departments should form a mutually restrictive relationship.
  • The production coordination meeting is generally hosted by the Planning Department, and must be attended by the Production Department, Procurement Department, Quality Control Department, and some Business Department and Technology Department


 楼主| 发表于 2022-11-15 20:45:54 | 显示全部楼层


第三,三要素法。
标准:生产协调会一定要形成决议。开了会没有决议,决议写成文字不追究、不跟进,完成、完不成又不管,这样的生产协调会根本就是在做无用功。
制约:要把任务明确地布置下去,并形成标准,将任务分配到人,将责任落实到岗。
责任:必须由稽核部对完成情况进行跟进检查、总结,进行责任追究和奖罚。


 楼主| 发表于 2022-11-15 20:47:18 | 显示全部楼层



Third, the three element method.
  • Standard: The production coordination meeting must form a resolution. There was no resolution at the meeting, and the resolution was written in words without investigation or follow-up, and the production coordination meeting was basically futile.
  • Constraints: we should assign tasks clearly, form standards, assign tasks to people, and assign responsibilities to posts.
  • Responsibility: The Audit Department must follow up, check and summarize the completion, and investigate the responsibility, reward and punishment
  • Resolution, follow-up inspection and rewards and punishments together constitute the three elements of the production coordination meeting.
  • In fact, the production coordination meeting held by many enterprises is not effective, which is due to the lack of the three element method. For example, when the water is boiled to 99 ℃, the difference is 1 ℃, which means that it does not boil.





 楼主| 发表于 2022-11-15 20:48:23 | 显示全部楼层
本帖最后由 gaowenhua 于 2022-11-15 20:50 编辑

数据控制法。
生产协调会是生产型会议,参会的各部门要带着表单、数据来,带着表单、数据走。前一天的任务成为数据在表单中体现,下一天的任务也要以数据体现,在表单上列明,这是生产协调会的基本要求。生产协调会要统计任务的完成情况,要有完成率、合格率,这些都是数据,生产协调会离不开数据。


 楼主| 发表于 2022-11-15 20:50:30 | 显示全部楼层
Data control method.

  • The production coordination meeting is a production meeting. All departments participating in the meeting should bring forms and data to the meeting and take them with them.
  • The task of the previous day should be reflected in the form as data, and the task of the next day should also be reflected in data, which is the basic requirement of the production coordination meeting.
  • The production coordination meeting shall count the completion of tasks, including the completion rate and qualification rate, which are all data. The production coordination meeting cannot be separated from data.



发表于 2022-11-17 08:14:31 | 显示全部楼层
Thanks a lot  for sharing.....
发表于 2022-11-17 09:53:23 | 显示全部楼层
提示: 作者被禁止或删除 内容自动屏蔽
您需要登录后才可以回帖 登录 | 立即注册

本版积分规则

手机版|小黑屋|QPDCA平台自律公约|QPDCA质量论坛 ( 苏ICP备18014265号-1 )

QPDCA质量论坛最好的质量管理论坛 GMT+8, 2024-12-4 18:08 , Processed in 0.099123 second(s), 17 queries , Gzip On.

无锡惠山区清华创新大厦901室0510-66880106

江苏佳成明威管理咨询有限公司 版权所有

快速回复 返回顶部 返回列表